CITY OF PICKERINGTON

SERVICE COMMITTEE OF COUNCIL

CITY HALL, 100 LOCKVILLE ROAD

THURSDAY, SEPTEMBER 8, 2005

 

WORK SESSION

6:00 P.M.

 

REVIEW OF PROPOSED 2006-2010 CAPITAL IMPROVEMENTS PLAN

 

                                                 REGULAR MEETING AGENDA

                                                                             

7:30 P.M.

 

1.         ROLL CALL

 

2.         A.        APPROVAL OF MINUTES OF AUGUST 2, 2005, Special Meeting

            B.         APPROVAL OF MINUTES OF AUGUST 11, 2005, Regular Meeting

 

3.         COMMUNITY COMMENTS:

 

4.         PLANNING AND ZONING DEPARTMENT

 

A.        REPORTS

(1)        Board of Zoning Appeals (Mr. Schultz)

(2)        Planning and Zoning Representative Report (Mr. O’Brien)

 

B.         ACTION ITEMS:  NONE

 

            C.        ACCESS MANAGEMENT PLAN:

 

5.         SERVICE DEPARTMENT

 

A.        REPORTS:

            (1)        Utility Fees Review Committee Representative Report (Mr. Hackworth)

 

B.         ACTION ITEMS:       

 

C.        WATER UTILITY MAINTENANCE

 

            D.        WASTEWATER UTILITY MAINTENANCE: 

                        (1)        EPA 208 Plan - Update

 

E.         STREET MAINTENANCE: 

                        (1)        Annual Street Repaving Project - Update

           

            F.         STORM WATER UTILITY MAINTENANCE

            (1)        Long Road/Bowen Road Stormwater - Update

 

G.        TREE COMMISSION.  Update

 

6.         ENGINEERING DEPARTMENT CAPITAL PROJECTS

 

A.        WASTEWATER

(1)        Wastewater Plant Expansion - Update

                        (2)        D-Line Interceptor Sewer Phase IIIB - Update

                                   

B.         TRANSPORTATION

            (1)        Courtright Drive

                        a.         Courtright Drive Extension Project, Phase III  - Update

 (2)       Diley Road Realignment

                        a.         Diley Road/S.R. 256 Intersection Improvement Project, Phase II – Update

                        b.         Diley Road/S.R. 256 Intersection Improvement Project, Phase III – Update

                        (3)       Diley Road Improvements Project

                                    a.         MORPC/ODOT Project – Update

                                    b.         Noise Barriers - Update

                        (4)        Cover/Ebright Connector

                        a.         Pickerington Health Care Access Road - Update

            (5)        Traffic Signal Update

           

            C.        WATER: 

            (1)        Wellfield Investigation – Update

 

D.        STORMWATER:  No Report

 